August | 2023
Client:
Swedish Medical Center
Project Role:
Electrical Engineering, Engineer-of-Record
Contract Engagement:
November 2022 to August 2023
Swedish First Hill UPS Replacement Project
Project scope included the electrical design for the replacement of an end-of-life age Central UPS and associated battery cabinet with new equipment. Design included evaluation of existing infrastructure and existing space so that replacement equipment fit in the space allocated and met all Code required and Facilities required working clearances. Engineering included review of existing distribution and new Central UPS equipment for selective coordination, available fault current, and arc flash.